Biosolids and Odor Control Project Update August 2005
Metro Water Services (MWS) is pleased to provide this update on the status of the Biosolids and Odor Control Project. There are three separate project elements included in this effort to upgrade our Central and Dry Creek wastewater treatment facilities, protect the environment and become a better neighbor to the community.
Please Join Us at a Community Meeting for Central Biosolids Project on August 23
Design and pre-construction activities for the Central Biosolids Project are underway with the design/build team composed of Archer Western, Earth Tech, Barge Wagonner Sumner & Cannon and Tighe & Bond. To kick off this $117.8 million project, a community meeting will be held on August 23 to share details regarding the site layout, architectural features and appearance of the completed facility.
What: Community Meeting for Biosolids Project
When: Tuesday, August 23 at 6 p.m.
Where: Neuhoff Complex on Monroe Street in East Germantown
Agenda:
1. Update on the status of the biosolids and odor control project at Central
2. Introduction of the design/build team
3. Presentation on site layout and facility architecture
4. Opportunity for community comments and questions
The scope of the project calls for construction of a new solids handling facility, including the addition of digestion and heat drying facilities, which will convert sludge into biosolids for reuse as fertilizer.
http://app.e2ma.net/app/view:CampaignPublic/id:663.115407328
Excerpt below:
Biosolids and Odor Control Project Update August 2005
Metro Water Services (MWS) is pleased to provide this update on the status of the Biosolids and Odor Control Project. There are three separate project elements included in this effort to upgrade our Central and Dry Creek wastewater treatment facilities, protect the environment and become a better neighbor to the community.
Please Join Us at a Community Meeting for Central Biosolids Project on August 23
Design and pre-construction activities for the Central Biosolids Project are underway with the design/build team composed of Archer Western, Earth Tech, Barge Wagonner Sumner & Cannon and Tighe & Bond. To kick off this $117.8 million project, a community meeting will be held on August 23 to share details regarding the site layout, architectural features and appearance of the completed facility.
What: Community Meeting for Biosolids Project
When: Tuesday, August 23 at 6 p.m.
Where: Neuhoff Complex on Monroe Street in East Germantown
Agenda:
1. Update on the status of the biosolids and odor control project at Central
2. Introduction of the design/build team
3. Presentation on site layout and facility architecture
4. Opportunity for community comments and questions
The scope of the project calls for construction of a new solids handling facility, including the addition of digestion and heat drying facilities, which will convert sludge into biosolids for reuse as fertilizer.